Truffle Nation · New Campus Premises · July 2026

Eleven non-negotiables, one registration date.

Every condition the lessor must meet before Truffle Nation signs — air conditioning, water, power, NOCs and lease terms — mapped onto the day-by-day path from today's meeting to registration on 30 July and construction kickoff on 1 August.

11
Non-negotiables
30 Jul
Target registration
8 days
24 Jul → 1 Aug path
01

The 11 Non-Negotiables

These are the conditions the premises must satisfy — as lease clauses or as pre-registration deliverables. Tick each one only when it is confirmed in writing or physically verified. Tap any item to expand the detail.

Tip: bring this checklist to every lessor conversation. Four of these items are on today's meeting agenda (marked with an agenda tag below) — resolve them before the contract goes to drafting on 28 July.
Building Works
AC installation must be 50–75% finished before the registration date. This is the gate condition on 30 July — wall demolition and AC progress are tracked through the 25–27 July update window.
Utilities & Power
Non-negotiable: a committed 3,000-litre share from the common tank, or dedicated separate tank(s) of at least 2,500 litres, guaranteeing continuous daily water supply. Separate-tank feasibility is on today's agenda. On 24 Jul agenda
Backup power capable of running multiple heavy-load machines — or, failing that, dedicated space to install a 65 KV diesel genset. A status update is due in today's meeting. On 24 Jul agenda
Sanctioned electricity load raised to up to 75 KV. Today's meeting covers the sanctioned load on the bill and how billing is calculated, since the load spans different premises. On 24 Jul agenda
Compliance & NOCs
Physical space for the signage board plus a written NOC from the building. Space possibilities and the NOC are on today's agenda; installation is scheduled for 1 August. On 24 Jul agenda
Either a Fire Safety NOC for the premises, or fire alarm installation where the NOC route isn't available.
Access & Operations
Parking space provision at the premises.
Students must be able to use the building lifts without restriction throughout school operational hours.
The building must accommodate Truffle Nation's operational hours of 9:00 am to 6:30 pm, as per company policy.
Commercial & Lease Terms
The lease must specify a notice period of 6 to 12 months, applicable after the lock-in period ends.
Property tax on the premises is the lessor's responsibility, not Truffle Nation's.
02

The Critical-Path Timeline

Eight days from today's lessor meeting to construction kickoff. The diamond marks the gate: registration on 30 July happens only after the lessor's work is complete.

24 July Today
Lessor meeting — four open points
  • Electricity bill sanctioned load discussion; bill calculation across different premises
  • Separate water tank installation, if possible
  • Signage board space possibilities and building NOC
  • Power backup update
25 – 27 July · by EOD
Wall demolition & AC installation process update
Progress update due on demolition and the AC install — this is what moves R1 toward its 50–75% pre-registration threshold.
28 – 29 July
Legal contract drafting & confirmation by both parties
Contract drafted and confirmed by both sides, with the final contract update issued by Truffle Nation. All 11 non-negotiables should be resolved or written into the draft by now.
30 July · The Gate
Registration — after lessor work completion
Registration proceeds only once the lessor's work is complete — AC at 50–75%, utilities committed, NOCs in hand.
1 August
Signage installation & construction work initiation
With registration done, Truffle Nation installs signage (per the R4 NOC) and begins its own construction work.
Watch: the 30 July registration is conditional, not fixed. If AC progress, water, power backup or any NOC slips past 29 July, the registration date — and the 1 August construction start — slip with it.
03

Today's Meeting — 24 July Agenda

Four points to walk out of today's meeting with clear answers on. Each maps directly to a non-negotiable from Section 01 — tick them as they're resolved.

Electricity: sanctioned load & bill calculation
Discuss the sanctioned load on the electricity bill and how billing is calculated, given the load is split across different premises.
→ R6 · 75 KV
Separate water tank installation, if possible
Feasibility of a dedicated tank (≥2,500 L) versus the 3,000 L common-tank share.
→ R2 · Water
Signage board space possibilities & NOC
Confirm where the board can go and secure the building's No-Objection Certificate.
→ R4 · Signage
Power backup update
Status on backup provision for heavy-load machinery — or confirmed space for the 65 KV genset.
→ R3 · Backup
Why today matters: the contract goes to legal drafting on 28 July. Anything left ambiguous after this meeting either becomes a hole in the contract or a delay to the 30 July gate.
04

Who Owns What

A clean split of responsibility, so nothing falls between the two parties in the contract.

Lessor delivers

Before registration · 30 July
  • AC work completed to 50–75%
  • Water: 3,000 L common-tank share or ≥2,500 L separate tank
  • Power backup for heavy machinery, or 65 KV genset space
  • Electricity load increased up to 75 KV
  • Signage board space + building NOC
  • Fire Safety NOC or fire alarm installation
  • Parking space
  • Unrestricted student lift access in school hours
  • Property tax (ongoing)

Truffle Nation delivers

28 July onwards
  • Final contract update (28–29 July)
  • Registration on 30 July, once lessor work is complete
  • Signage installation from 1 August
  • Construction work initiation from 1 August
Joint: legal contract drafting and confirmation by both parties, 28–29 July. Lease terms to encode: 9:00 am–6:30 pm operational hours (R9) and a 6–12 month notice period after lock-in (R10).