Eleven non-negotiables, one registration date.
Every condition the lessor must meet before Truffle Nation signs — air conditioning, water, power, NOCs and lease terms — mapped onto the day-by-day path from today's meeting to registration on 30 July and construction kickoff on 1 August.
The 11 Non-Negotiables
These are the conditions the premises must satisfy — as lease clauses or as pre-registration deliverables. Tick each one only when it is confirmed in writing or physically verified. Tap any item to expand the detail.
The Critical-Path Timeline
Eight days from today's lessor meeting to construction kickoff. The diamond marks the gate: registration on 30 July happens only after the lessor's work is complete.
- Electricity bill sanctioned load discussion; bill calculation across different premises
- Separate water tank installation, if possible
- Signage board space possibilities and building NOC
- Power backup update
Today's Meeting — 24 July Agenda
Four points to walk out of today's meeting with clear answers on. Each maps directly to a non-negotiable from Section 01 — tick them as they're resolved.
Who Owns What
A clean split of responsibility, so nothing falls between the two parties in the contract.
Lessor delivers
- AC work completed to 50–75%
- Water: 3,000 L common-tank share or ≥2,500 L separate tank
- Power backup for heavy machinery, or 65 KV genset space
- Electricity load increased up to 75 KV
- Signage board space + building NOC
- Fire Safety NOC or fire alarm installation
- Parking space
- Unrestricted student lift access in school hours
- Property tax (ongoing)
Truffle Nation delivers
- Final contract update (28–29 July)
- Registration on 30 July, once lessor work is complete
- Signage installation from 1 August
- Construction work initiation from 1 August